After much deliberation, I have decided to insulate the entire building internally with 45mm rock wool. I will therefore use the studs for the insulation compartments to also relieve all loads that land above the windows. I will place XPS300 where these loads occur. Yes, it is overly strong XPS, but on the other hand, the load will be right at the edge of the slab.

Thinking of just adding two longitudinal rebar (10mm iron) where the loads occur, to complement the 6-150 reinforcement mesh. Hard to see stirrups being needed for small loads like 5-10kN or do you think some iron in the other direction is also needed? (That is, from the outside inward). 100mm concrete everywhere. So no thickened edge or edge beam. Interior construction site with exposed brick wall, blue plastic covering a window, and a wooden beam supporting the ceiling. Insulation materials on the floor. An old window in a concrete wall with visible cracks and exposed bricks, located in an unfinished interior renovation site.
 
S
I had placed some rebar under the mat and inward. The mat does not contribute to strength but rather helps to reduce surface cracks. Two rebars in the longitudinal direction should be sufficient. Ideally, you would want two at the top and two at the bottom since they handle both tensile and compressive forces, but it becomes too cramped to manage that properly in 10 cm.
 
Last edited:
  • Like
Gabsson
  • Laddar…
S Söne said:
I would have inserted some rebar under the mat and inward. The mat doesn't do anything for strength but helps reduce surface cracks. Two rebars in the longitudinal direction should hold it. Ideally, you want to have two on top and two on the bottom because the two handle both tensile and compressive forces, but it's too tight to manage that sensibly with 10 cm.
In theory, I would have wanted thicker casting there, but somewhere you have to set the limit for safety margins.
The reason I have exactly XPS300 is to reduce the tensile stress on the slab, which decreases if the substrate is hard and even.
The load that arises should be the one wanting to crack the edge of the slab, but there I have the existing interior wall to hold against.

I have placed a Jackon Jackopor wet room board along all walls to create a diffusion barrier between the existing base and the new concrete floor. It also insulates a little but is only 12mm thick. But mainly to create a floating floor that is not anchored to the old one, hopefully reducing the risk of cracks.

I also want to add that along the new concrete floor, I will lay a wooden beam on edge, type 45×195, to distribute the load on the floor. So, it will not be a typical point load but rather a line load. A corresponding beam will lie under the glulam beam since there is span there.
 
Last edited:
Underfloor heating installation with LK Systems 16 mm and C-C 240 mm spacing, featuring pipes and ducts, showing a separate casting form for the bathroom. Underfloor heating installation with LK systems 16 mm pipes, spaced 240 mm apart. Separate mold for bathroom with EPS cement visible.
Underfloor heating LK systems 16 mm. C-C 240 mm.
Separate mold for the bathroom as EPS-cement will be used there.
 
Concrete pouring scheduled for November 3rd. Here is how it looks today.
Reinforcement mesh 6-150
Reinforcement bars 10mm where point load exists.

Steel reinforcement mesh on concrete floor with wooden beams above, ready for concrete pour. Exposed wiring and brick walls visible in the room. Reinforcement mesh and rebar layout for concrete casting near a window with worn plaster wall. Reinforcement mesh laid on a construction site with a cracked plaster wall and small window above. Reinforcement mesh and bars are laid on a concrete floor with visible pipes and an old brick wall in the background. Reinforcement mesh with 10mm rebar near point loads on a construction site floor, preparing for concrete casting on November 3rd.
 
  • Like
Söne and 1 other
  • Laddar…
Flat on site November 3. Have a separate thread for it if anyone is interested.
Concrete slab freshly poured inside a building under construction, dated November 3, with visible plastic coverings and construction materials.
 
Back to the walls then.
I chose to insert a type of flexible rebar called helibars. They are 6 mm and absorb tensile stresses in the construction. I have embedded these with a thixotropic mortar, like cement paste.

A close-up of a twisted helibar, a type of flexible reinforcement bar, used for tension absorption in construction. Flexible reinforcement bar, known as helibars, inserted into brick wall joint with thixotropic mortar, enhancing structural tension support. Close-up of a wall with a helibar inserted, showing a flexible reinforcement bar embedded in mortar, used to absorb tensile stress in construction. Flexible helical bar embedded in a wall with cementitious mortar, displaying reinforcement method for tension absorption.
 
  • Like
Söne
  • Laddar…
As you know, I will stud all the walls to insulate 45mm. Then I will take the opportunity to relieve all the roof trusses as well so that not all the load ends up on the brick walls.

Now I will re-grout all the joints I have routed out, with hydraulic lime mortar NHL 3.5, also known as D-bruk.
 
Feedback.

Regarding the relief of the glulam beam above this window, I have used the following loads.

Point load from the roof is approximately 11 kN.
As the overhead beam, I will use 220×45.
The span is 820 mm. It should handle about 21 kN with a point load in the middle. Calculated only on the breaking limit and not deformation.

For posts, it will be 45×95mm. They should handle 7.52 kN with a buckling length of 2m, so a total of about 15 kN.

So in this case, the posts set the limit. Against the concrete, we have nailed in a 45×45 (you could call it a sill). This distributes the load a little on the concrete.
A window in an unfinished wall with visible bricks and wood beam installation. An envelope rests on the window sill, and cables run along the floor.
 
Now the offloads are shaping up.
Everything from 45×220 to 45×265 beams.
The posts are not ready yet but will be 45×120
Wood beams installed on a construction site with partially finished walls and insulation visible, along with construction materials on the floor. Wooden beams and insulation in a partially renovated room with exposed brick walls and old windows. Construction materials are scattered on the floor.
 
Small update.
All new windows (Elitfönster Retro) and doors (Diplomat) are now installed.
The walls consist of 45mm studs with 70mm insulation, Isover Vario Xtra, OSB board, and gypsum board. In the bathroom, we used construction plywood and regular gypsum. The waterproofing will be wet room membrane followed by tiles.

Renovation scene with tools and materials, showing a partially constructed room with a person in work attire inspecting the site under bright lighting. Bathroom under renovation with new window installed, white pipes protruding from the wall, fresh concrete floor, and unfinished drywall on the walls. Renovation project with newly installed window, toilet, drywall on walls, and ceiling light in a bathroom under construction. Renovation in progress with new drywall installed, temporary lighting setup, and tools on the floor in a room being updated with windows and doors. Red-framed window with snowy reflection, showing a person taking a photo.
 
  • Like
MultiMan
  • Laddar…
So here, about 6 months after the project started, it turned out like this. A standing seam metal roof remains when the weather improves. Lots of problem-solving along the way with concrete calculation, reinforcement, loads and counterloads, glulam beams, insulation, etc. I am still satisfied with the final solutions I've chosen. The only potential risk construction is the roof where I skipped the air gap and instead used Isover Vario Xtra. However, I have very good ventilation in the house and the vapor barrier is tight everywhere, meaning no gaps.

Thanks to everyone on the forum who helped me along the way!

NOTE: approximately 950,000:- poorer despite about 200 hours of my own effort.

Renovated kitchen and living area with beige flooring, dark cabinets, and recessed ceiling lights. A wooden beam divides the space. A modern kitchen with gray cabinets, a built-in oven, and a window above the sink, showcasing the renovation progress after six months of work. Modern bathroom with a tiled floor, white walls, a shower with glass doors, a washing machine, and a window letting in natural light. Minimalist room with a bed, hanging lamp, and door leading outside. Unfinished interior with visible ceiling panels and window to the left. Renovated bedroom with slanted ceiling, wooden beam, bed with two wooden towels, a pendant light, and a window with a view outside. A newly renovated living room with concrete floors, a sofa, a wooden dining table, and modern lighting fixtures, reflecting ongoing home improvement work.
 
Last edited:
  • Like
Klodsmajor and 11 others
  • Laddar…
Click here to reply
Vi vill skicka notiser för ämnen du bevakar och händelser som berör dig.