Hello hello!
I'm working on a university assignment here that involves the casting of a wall and how to go about it. We're tasked with arranging the various steps in order and drawing up a process map/action plan on how to perform the casting and identifying the critical points and steps that must be completed before moving to the next step. The points listed below:
  • Reinforcement
- cutting & bending - transport by crane - laying
Demolding
Formwork
- setting up wall formwork including transport by crane
- installation of stoppers & openings
- doubling of wall formwork
Casting
- preparations for casting
- filling of the bucket
- transport to and from the concrete pocket
- emptying the bucket and vibrating
Installation of electrical material
Positioning – may be relevant at several occasions

The steps are not arranged in the correct execution order, and that's what we need to do. If I were to guess, I would think:
1. Positioning
2. Formwork
3. Reinforcement
4. Installation of Electrical
5. Casting
6. Demolding

Quite unsure so tips/help would be greatly appreciated! :)
 
Assuming the slab the wall will stand on is complete, the reinforcement from it is required.
Then follows:
Layout
Form one side
Reinforcement coordinated with installations and recesses
Form the other side (you close the form)
Casting
Dismantling

These are very basic steps.
It omits steps like bracing, alignment, self-inspection, spacers, high-pressure washing, oiling the form, and many more steps.
 