I need help from someone who works with bathrooms/tile setting. We have an electrician who laid floor heating coils directly on chipboard (quicknet) and says the tiler should reinforce (if needed) on top.
When the tiler sees it, it stops - he refuses to lay reinforcement on top and cast on it...
who made a mistake, or is there a good way to proceed now?
 
Last edited:
Don't know what the spec is on "quicknet," but when you lay regular t2 blue on chipboard, you should always have the reinforcement under the cable at least. I would think the same applies in this case. But as mentioned, I have never laid that particular system (y)
 