Hello.

We are going to build a 1.5-story house with isolec blocks 350 mm. We have already signed a contract with a contractor who now, 2 months later, says they cannot construct the gables under the ridge because it would be too unstable. Instead, they would be built in wood and covered with a sheet of plaster on the outside.

It feels unprofessional to come with this so late. Is this correct?

Thanks in advance. Urgent.
 
We have built a 6.5-meter high 1.5 story house in Isoleca. It requires some construction work, but not too extensive. I paid 18,000 SEK for construction drawings. Not so much for the gables, more concerning the long sides. Strong roof trusses brace the gables. Maybe they find it difficult to work from scaffolding with masonry.
 
  • A partially constructed 1.5-story house in Isoleca with a metal roof and multiple windows, surrounded by construction debris and a green dumpster in the yard.
  • Front view of a partially constructed 1.5-story house with exposed concrete blocks, multiple windows, and surrounding construction materials in a rural setting.
Hello kalarne.
Thank you so much for the response.
 