P
Hi,

We are at the starting point of building an extension and have now started brainstorming how it should look before we involve an architect and engineer to come up with new ideas ;)

It will be a concrete slab 9*6 m on stable rock/moraine. Basement with lecablock, middle floor, and upper floor (1.5 floors). One problem we have is that we would like to make the basement part a living space, and there are requirements for 2.4 m (2.3 m works too?) ceiling height. Today we have 2.12 m in the existing basement and 0.48 cm between floors. To avoid a higher floor in the new part on the middle floor, we need to "gain" 18-28 cm plus a minimum of 4 cm for the floor drain for the shower (drainage line 2 m plus one cm slope towards the drain plus one cm fix and tile). The only option we have to gain is on the floors, or by raising the floor in the shower to get a natural slope to the old house's 110-line in the laundry room.

48 cm between floors is:

1.5 cm parquet
0.5 cm underlay foam
2.2 cm flooring chipboard
39 cm beams
2.2 cm bearing battens for basement ceiling
1.3 cm gypsum

7.7 cm I can't save on in the new part. So there are 40 cm left. I need to save 18+4=22 cm (if the requirement is 230 cm) or 28+4=32 cm (if the requirement is 240 cm).

I realize that 7 cm (39-32 cm) beams are not feasible, and that I, with a ceiling height requirement of 240 cm, must raise the shower floor drain a bit...

But HEB beams in the whole basement floor? Max span 4 m. Load two floors (2 kN/m2), continuous load-bearing walls throughout the building (45*120), snow zone 2.5. Exterior walls 45*195+45*45.

All ideas, thoughts, and tips are GRATEFULLY received!

Best regards, Joakim
 
Wouldn't it be easier to lower the foundation level and have the new basement floor lower than the old one? Or do you have other problems with that?
 
P
GoC GoC said:
Wouldn't it be easier to lower the foundation level and have the new basement floor lower than the old one? Or do you have other problems with that?
Yes, then I would have to pump the shower water to a suitable point. The kitchen drain and the toilet (wall-mounted) in the basement can be solved more easily.

So, ideally, I want to solve the problem with a lower height on the intermediary floor, and possibly raise the shower floor somewhat, while preferably having a ceiling height of 230 cm.
 
Last edited by a moderator:
Do the beams for the intermediate floor have a span of 6 m? What dimensions, c/c mm, have you calculated?
 
Is there a need for 2.4m? We have 2.2 and it works for living in.
 
Prefabricated prestressed concrete floor slab.
And then you lay the sewage in the ceiling of the basement instead of in the floor slab.
 
P
J justusandersson said:
Do the beams for the intermediate floor have a 6 m span? What dimensions, c/c mm, did you calculate on?
The entire extension will be 6*9 m, so the free span outside the Leca blocks in the basement is thus a minimum of 5.5 m.

CC600 generally, but CC300 at the toilet on the middle floor.

Same thing on intermediate floor number 2, but the rules are 19 cm, so the maximum free span is 5.62 m.

One thing I'm trying to achieve is to have interlayers with a load-bearing wall all the way down from the basement. But the dining room will be large and open on the middle floor, and on the upper floor, a large master bedroom.

For the basement floor, I have found:
* Glulam beam 90*225 minimum but 115*225 is better. This leaves minimal room for a gradient solution in the basement. CC600 yields 15 pieces, approximately 20,000 SEK. Uncertain soundproofing.
* Prefab concrete hollow core slab 200 mm, free span 6 m. Probably expensive...
* Leca lightweight concrete slab, 200 mm, free span only 5.38 m (5.5 needed unless we want to push the wall in by 12 cm, which feels a bit unnecessary). Uncertain price but good fire protection and soundproofing. No floor particle board needed and plaster on the underside saves about 5 cm compared to the corresponding construction.
* Steel beam, HEA 180, strong, 15 pieces of 6 m cost about 20,000 SEK. Must be painted with fireproofing foam.

For the intermediate floor from middle to upper floor, a steel beam HEA180 or glulam beam 115*225 only works (floor today about 25 cm). So around 20,000 SEK regardless.

Roof beams of glulam with longitudinal placement, 5 pieces 115*315 *9000. Cost about 15,000 SEK. Then 45*220 on top to get a lot of insulation in the roof (500 mm) and roof boards.

That's about as far as I've thought now.
 
P
L largab said:
Is there a need for 2.4m? We have 2.2 and it works to live in.
According to PBL, 2.3 m is required (it says 2.4 m on the municipality's website for permanent residence) for basement/terrace floor, which I hope applies. 2.4 m means external pumping is needed :(
 
P
GoC GoC said:
Prefab post-tensioned concrete slab.
And then you place the drainage in the ceiling in the basement instead of in the slab
It's the shower in the basement of the new build that's causing issues, not from the middle floor and upper floor. The connection to the existing drainage, which is under the floor in the existing basement with a ceiling height of 2.1 m :(

The difference of 2.1 vs 2.3 plus the slope in the shower, adhesive+tiles+slope on the new line 3 m is what needs to be "earned" unfortunately.
 
A completely equivalent alternative to glulam 115x225 is glulam 215x180. Slightly more expensive due to the unfavorable relation between width and height, yet still much cheaper than steel. I haven't calculated the loads, but it will surely work with c/c 600 mm. Soundproofing should not be a major issue in this case.
 
  • Like
Anonymiserad 184001
  • Laddar…
P
A few quick sketches. As you can see, continuous load-bearing walls down to the basement are difficult :( But sufficiently rigid intermediate floors should solve it.
 
  • Hand-drawn basement floor plan sketch showing room dimensions, wall placements, and notes on load-bearing challenges and floor stiffness.
  • Hand-drawn floor plan sketch showing room dimensions and layout for a renovation project, highlighting both new and old sections.
  • Hand-drawn floor plan sketch showing master bedroom, WC, cabin, and an extension of a house, detailing measurements and structural notes.
It's quite a common problem with extensions, the difficulty of achieving continuous load-bearing walls. This is a more elegant solution. The floor chipboard needs to be screw-glued to keep the flex under control.
 
P
J justusandersson said:
It is quite a common problem in extensions, the difficulty in achieving continuous load-bearing walls. This is a more elegant solution. The floor chipboard needs to be screwed and glued to keep the flex under control.
If you instead go for HEA180, the cost is comparable, but it should be stiffer as well, right? The only problem is probably sound transmission and fire protection. HEB seems a bit too expensive.
 
P
GoC GoC said:
You "gain" nearly 30cm with prefab concrete beams
[link]
I only find one at 185 mm which is 40 mm better than glulam (115*225)? Concrete is great for fire protection but sound travels quickly :( The requirement from the wife to rent out the apartment is that it should be well soundproofed.
 
Vi vill skicka notiser för ämnen du bevakar och händelser som berör dig.