I am building a greenhouse/orangery and wondering how to fill the gap seen at ground level between the foundation and the L-support.
Background: We started by placing L-supports around the patio and then filled/compacted with 0/32 crushed stone. On top of that, we laid a frame with form blocks and cast with concrete to create a foundation for the greenhouse. Then we built with lecablock on top of the concrete frame.
Question: If I fill the gap with gravel, there will be some voids between the stones. In winter, there is a risk that the 0/32 base is frozen and doesn't allow water to pass through, so the trench filled with gravel fills with water that then freezes. Can this crack the concrete frame?