L luppe #1 Member · 61 posts 21 Jul 2007 at 8:34 PM luppe Member 61 posts 21 Jul 2007 at 8:34 PM #1 Hi, how long does it take for the concrete to dry if you have filled a well in the basement? /Bosse
A andersmc #2 Member · Blekinge · 9 629 posts 21 Jul 2007 at 10:51 PM andersmc Member Blekinge 9,629 posts 21 Jul 2007 at 10:51 PM #2 The concrete sets in one day. Then, it should be left alone for a couple of weeks before building around it or covering it with anything.
The concrete sets in one day. Then, it should be left alone for a couple of weeks before building around it or covering it with anything.
J jon_h #3 Member · Uppsala · 7 851 posts 23 Jul 2007 at 12:05 PM jon_h Member Uppsala 7,851 posts 23 Jul 2007 at 12:05 PM #3 Normally at least four weeks before spackling, or 1-3 months before tiling, depending on which products are used.
Normally at least four weeks before spackling, or 1-3 months before tiling, depending on which products are used.