Hi, how long does it take for the concrete to dry if you have filled a well in the basement?
/Bosse
 
The concrete sets in one day. Then, it should be left alone for a couple of weeks before building around it or covering it with anything.
 
Normally at least four weeks before spackling, or 1-3 months before tiling, depending on which products are used.
 