I am about to install a ceiling with two layers of plasterboard. The outer layer should be screwed every 20 cm along the outer edge and every 30 cm along the joists. I haven't found any information if the same applies to the first layer, or if it can be screwed more sparsely?
Grundstött
· Halland
· 28 345 posts
Why so much plaster in the ceiling?
Is it noisy from the neighbor above?
But if you just fasten the first layer so it doesn't fall down, the screw in the next layer will hold everything in place.
Just not too short screws
Is it noisy from the neighbor above?
But if you just fasten the first layer so it doesn't fall down, the screw in the next layer will hold everything in place.
Just not too short screws
It is indeed the attic above, but footstep sounds are very clear, and since the room will become a bedroom, I have done my best to make it a soundproof ceiling. Steel studs hanging on sound clips and two layers of plaster.KnockOnWood said:
As mentioned, you only need to screw the first layer so that it is held up until the second layer comes up. Then the ceiling should be framed with a 300mm center-to-center distance. And don't forget to stagger the joints, and use metal straps in the joints on the last layer.
Click here to reply
Similar threads
-
Gypsum board reinforced with plywood - how to fasten?
Building Materials and Construction Technology -
Radonskydd med plastfolie - mot flisbädd eller ovanpå första lagret cellplast?
Grund & Markarbeten -
Double drywall ceiling, which drywall for the first layer? Without recessed edge?
Building Materials and Construction Technology