Approximate cost of having a fence built (preferably quick answer:))
Hi! Quick responses would be greatly appreciated 
We had our fence knocked down by a reckless driver, and we're trying to make an insurance claim. Does anyone know the approximate cost for the following (including labor, as we don't have time to do this ourselves):
Twelve meters of fence, eight posts to be anchored and set in concrete with dimensions approximately 100x100. About one meter high fence, a total of 120 slats (one meter long). A couple of cross beams per section. I estimate the material cost to be a few thousand, but the labor cost? Without rotavdrag? The ground isn't particularly rocky, so anchoring the posts shouldn't pose any more problems than usual. Very grateful for any answers!
We had our fence knocked down by a reckless driver, and we're trying to make an insurance claim. Does anyone know the approximate cost for the following (including labor, as we don't have time to do this ourselves):
Twelve meters of fence, eight posts to be anchored and set in concrete with dimensions approximately 100x100. About one meter high fence, a total of 120 slats (one meter long). A couple of cross beams per section. I estimate the material cost to be a few thousand, but the labor cost? Without rotavdrag? The ground isn't particularly rocky, so anchoring the posts shouldn't pose any more problems than usual. Very grateful for any answers!
Then the existing fence should probably be removed?
larsbj- have you missed all the posts about bathrooms? The prices in Stockholm are ridiculous.
here the quote will be something like - cutting of boards 144 pieces, 1 day, primer and two coats of paint 3 days, dismantling and removal 2 days. Casting 6 footings 2 days, mounting fence, including painting nail/screw holes 2 days.
total of 10 days.
larsbj- have you missed all the posts about bathrooms? The prices in Stockholm are ridiculous.
here the quote will be something like - cutting of boards 144 pieces, 1 day, primer and two coats of paint 3 days, dismantling and removal 2 days. Casting 6 footings 2 days, mounting fence, including painting nail/screw holes 2 days.
total of 10 days.
Now I saw that more people have responded. I don't log in that often. The place is in Malmö. So the prices probably differ significantly from what it costs in Stockholm. I'm waiting for a quote now to forward to the insurance company. Thanks for all the replies!