I need to hear from you "experienced" folks regarding the time required for some work tasks:

About 24 linear meters of studs installed in a rectangular ceiling - no leveling or similar, just 5 studs along the ceiling and one along the short side.
About 20 linear meters of studs installed in an adjacent rectangular ceiling, 7 studs along the ceiling and one along the short side.
Drywall and spackle two walls, both 250 cm in height, one wall 280 cm wide, the other 230 cm, each having a window of 140 * 100 cm breaking the wall.
10 vertical studs about 60 cm each, installed between two horizontal studs as extra support for upcoming OSB and drywall.

Grateful for feedback!!
 
Is there no one with an opinion? We think the snickare who did this has taken too long, but the construction company thinks the time spent is reasonable.
 
Questions like these pop up from time to time here on the forum, and it is very difficult/risky to sit and speculate how long a specific job "should" take. Maybe that's why no one has come up with any suggestions...........
 
P
What does "väl lång tid" mean?
 
Quite a long time - 20 hours. The thing was that I didn't want to state the time it took, but rather let someone with experience in such jobs give their view on what it should take without a preconceived notion.
 
Last edited:
max 1 day, that is max 8 hours. if the material is on site, electrician is available etc.
including doubling..
painter I do not know... but they putty this quickly...

regards
carpenter estwing
 
Tach estwing, that's something we also thought. Materials are here and it's the same person who did everything, i.e., also plastering.
 