Hi, I'm having trouble with the leveling compound not curing/drying completely? It's been applied on an uninsulated concrete slab with primer and electric heating cables, about 1-1/2 cm thick layer! I've used leveling compound about 6 times and have never encountered this before!?! It's about 15-18 degrees Celsius in the room, but the floor is cold... could it be that the cold floor is causing it to cure very slowly!???
It was probably quite cold water yes but 70% of the floor has burned... let's hope it finishes burning eventually, otherwise, it will mean digging out a part and pouring a new mix with lukewarm water! However, I can't remember mixing any of the other times with anything but cold water?! hmmm