Reasonable time to set up Steel Studs and wall?
Thanks for the quick reply! What a Forum! Length of the House 11 meters Gables 5 meters. No radiators. (Underfloor heating) 2 small windows with dimensions Height 67 cm, width 55 cm. 1 window with dimensions Height 93 cm, width 145 cm and finally 1 window that is height 64 cm and width 115 cm. 1 door with height dimension 198 cm and width 80 cm. Height from floor to ceiling after cast concrete floor is 2 meters and 20 cm. Not standard dimensions, of course...Mazen said:
No, unfortunately, not everything is straight and plumb. The house is an old log frame from a Härbre, which had a basement foundation cast for it once upon a time.
Knutes Ulf Persson said:
Thanks for the quick response! What a forum! Length of the house is 11 meters, gable ends are 5 meters. No radiators. (Underfloor heating) 2 small windows with dimensions Height 67 cm, width 55 cm. 1 window with dimensions Height 93 cm, width 145 cm and finally 1 window which is height 64 cm and width 115 cm. 1 door with height 198 cm and width 80 cm. Height from floor to ceiling after casting the concrete floor is 2 meters and 20 cm. Not standard measurements, then... No, unfortunately, not everything is straight and level. The house is an old timber frame from a Härbre, to which a basement foundation was cast once upon a time.
But the basement walls should still be cast/masoned vertically...
Okay, say it takes 2-3 hours to measure and level the top and bottom rails, then it's just about stacking the studs and screwing...
Okay, say it takes 2-3 hours to measure and level the top and bottom rails, then it's just about stacking the studs and screwing...