Prerequisite
A boiler room where an oil boiler is located. Door to outdoors, and door to laundry room.
Adjacent room is laundry room with door to boiler room and door to hall.
Want to merge and install geothermal heating.
What is the correct work order? I can do the work before moving in. The two spaces together are about 10 sqm.
Remove the oil boiler
Remove the wall
In parallel with the above, drill for geothermal heating
Install geothermal pipes/connection
Tile former boiler room and former laundry room, walls and floor
Install geothermal heat pump
Install washing machine, dryer, laundry sink, etc.
How long can the various steps be expected to take?