Number of craftsman hours to "plasterboard" entire house?
Ts.
Does it only concern exterior walls? Or should interior ones be included?
Otherwise, I guess about 120 hours. If the person performing the work knows how to do it and has the right tools.
With interior walls.
Sent from my LT26i using Byggahus
Does it only concern exterior walls? Or should interior ones be included?
Otherwise, I guess about 120 hours. If the person performing the work knows how to do it and has the right tools.
With interior walls.
Sent from my LT26i using Byggahus
Last edited:
I apologize for my absence.
The framing is already done. It applies only indoors. That is, regular plasterboard with chipboard behind. However, both ceiling and wall. No bay windows, but many electrical sockets...
But now I have an idea at least. As a non-carpenter, it's hard to know if a job takes two days or two weeks... 
The framing is already done. It applies only indoors. That is, regular plasterboard with chipboard behind. However, both ceiling and wall. No bay windows, but many electrical sockets...