D09 #1 Member · västra götaland · 9 427 posts 26 Mar 2010 at 10:18 PM D09 Member västra götaland 9,427 posts 26 Mar 2010 at 10:18 PM #1 Thinking about when to drill and install the wall penetrations for the air supply... Should you do it before the drywall is up or after? If you do it after, how do you seal at the vapor barrier?
Thinking about when to drill and install the wall penetrations for the air supply... Should you do it before the drywall is up or after? If you do it after, how do you seal at the vapor barrier?
N Niclas Jonsson #2 Member · Västra Götalands Län · 529 posts 26 Mar 2010 at 10:36 PM Niclas Jonsson Member Västra Götalands Län 529 posts 26 Mar 2010 at 10:36 PM #2 If you want it tight against the plastic, you need to fix it before the wallboard is up. Tape generously...
If you want it tight against the plastic, you need to fix it before the wallboard is up. Tape generously...