Hi,

I have a garage space that is divided into two "rooms" according to the simple cross-section sketch below.
The larger orange section is a loft with an associated stairwell and will be heated using a heat pump. The blue section will be a cold garage.
(of course, the exterior walls and roof are also insulated, I just haven't included that in the drawing.)

The orange section is wrapped in plastic, illustrated here with a green line.

My question is how should I deal with the red section of the plastic wrapping? I understand that you shouldn't wrap both sides of the insulation in plastic, which would happen if I wrap that part as well. At the same time, there will be heat leakage with potential condensation in the insulation if it's not wrapped.

What is correct? How should I proceed?
Grateful for all insights and thoughts!

Cross-section sketch of a garage space divided into two rooms, an orange loft area with a stairway and a blue cold garage. Green and red lines show plastic sheeting.
 
T
You should apply plastic to all the walls against the heated part, so from the lower green all the way around to the next green if you want to stop moist warm air from the orange part from entering the wall, in my opinion.
You are encasing the entire protrusion, but it's the warm side all around - what you should avoid is having plastic on both the warm and cold side.
 
I don't think you need to exaggerate everything. If the rest of the house is plastic-wrapped, make sure the exterior walls are wrapped. The walls that are then inside the house and garage are probably overdoing it to plastic-wrap, even though in theory it is warm and cold on different sides.
 
Steeldragon
S Stefan1972 said:
I don’t think there’s a need to overdo everything. If the rest of the house is wrapped in plastic, then make sure the outer walls are wrapped in plastic. The walls that are inside the house and garage are probably overkill to plastic wrap, even if in theory it is warm and cold on different sides.
The outer walls in the cold part are not wrapped in plastic. I might have been a bit unclear there. So it is only wrapped in plastic according to the green lines.
 
Steeldragon
T Testarn said:
You should cover all the walls towards the heated part, so from the lower green area all the way around to the next green, if you want to stop moist warm air from the orange part from going into the wall is my thought.
You're covering the entire protrusion, but it's the warm side all around - what you should avoid is having plastic on both the warm and cold side.
That sounds reasonable the way you present it. Thanks for the response!
 
The most correct way is probably to ignore isolating the short wall section and pull the plastic straight around the corner.

Diagram showing insulation and plastic around a short wall section with lines indicating material layers, related to a construction project discussion.

But, practically speaking, it doesn't matter if you pull the plastic around that wall too. Having plastic on both sides doesn't matter since the temperature is the same on both sides. Additionally, it's just a short wall section and open on one side.

I would have done it like this:

Diagram showing cross-section of a wall corner with insulation strategy, indicating plastic wrapping method for a short wall segment.
 