I have torn down a wall where the floor had grooves ranging from 1cm to 5cm deep, which I have filled with fine concrete. I need to self-level the entire area, which is in total around 1-1.5m2. On top of the filled grooves, a wall and door frame will be built, and otherwise, no flooring will be laid for at least a few months.
I find it difficult to determine how long I need to wait when I read on the bag for Byggmax fine concrete about the time I have to wait.
It is within the red rectangle that I will self-level, and the green lines are where the grooves with new fine concrete are.