Wondering in what order everything should be done when it comes to decorating the house...

trim, floors, stairs, etc... pipes, electricity, ventilation, etc...

Is there a list of how everything should be done from when there are outer walls inside without gypsum until everything is in place...?

For example, should the wooden floor be laid before the interior walls are erected, etc., when should the stairs go in, etc... there should be a list, I think :)

Can anyone contribute something more detailed? :S
 
Logical thinking and in some cases a bit of customization, I would say.

For example, it is smart to install permanent interior walls before laying the floor to avoid dirtying/scratching the floor. But a temporary "loose" interior wall should be placed on top of parquet, for example, to have a complete floor when the wall is removed one day.

Electrical wiring in interior walls is easiest done by electricians when you have boarded one side of the wall or before. It's good to have the ventilation sorted out before you wallpaper... ;-) hehe

Best regards,
Thomas
 