12,272 views ·
25 replies
12k views
25 replies
Joists for long span (6 meters)
Hello
I have a flat roof/terrace (4%) under design. While it is a garage roof, you can also use it as a terrace. The area is approximately 9.6 meters x 6 meters = just under 60 sqm.
I want to have rafters made of HEA beams mixed with pressure-treated lumber 45 x 145. All are securely anchored at both ends, and the span is 6 meters. I have assumed that HEA beams are much less expensive than laminated timber beams and save on ceiling height due to the greater strength of steel. 45 x 145 isn't particularly costly either.
I can no longer perform proper engineering calculations on this but have (as an old draftsman from the '70s) sketched this roughly and am looking for a skilled designer who could review:
With a spacing of 300cc over approximately 9600 meters, I have sketched with 31 rafters, i.e., 33 spacers of 300 mm.
The rafters alternately consist of lumber 45 x 145 and HEA 120 distributed with the main rule of 2 wood and one HEA. With a denser arrangement of HEA in the middle with every other being wood and every other being HEA (position 13 – position 18)
1 + 1 wood + 1 HEA will be in positions 1 -12 and 19 – 31, which gives 16 + 1 wood and 8 HEA.
In the middle, it becomes 1 wood + 1 HEA in positions 13-14, 15-16, 17-18, which results in 3 wood and 3 HEA.
A total of 20 wood and 11 HEA.
On the rafters, a metal roof, and on this, a joist and beams for UPM decking.
I have a flat roof/terrace (4%) under design. While it is a garage roof, you can also use it as a terrace. The area is approximately 9.6 meters x 6 meters = just under 60 sqm.
I want to have rafters made of HEA beams mixed with pressure-treated lumber 45 x 145. All are securely anchored at both ends, and the span is 6 meters. I have assumed that HEA beams are much less expensive than laminated timber beams and save on ceiling height due to the greater strength of steel. 45 x 145 isn't particularly costly either.
I can no longer perform proper engineering calculations on this but have (as an old draftsman from the '70s) sketched this roughly and am looking for a skilled designer who could review:
With a spacing of 300cc over approximately 9600 meters, I have sketched with 31 rafters, i.e., 33 spacers of 300 mm.
The rafters alternately consist of lumber 45 x 145 and HEA 120 distributed with the main rule of 2 wood and one HEA. With a denser arrangement of HEA in the middle with every other being wood and every other being HEA (position 13 – position 18)
1 + 1 wood + 1 HEA will be in positions 1 -12 and 19 – 31, which gives 16 + 1 wood and 8 HEA.
In the middle, it becomes 1 wood + 1 HEA in positions 13-14, 15-16, 17-18, which results in 3 wood and 3 HEA.
A total of 20 wood and 11 HEA.
On the rafters, a metal roof, and on this, a joist and beams for UPM decking.
Member
· Blekinge
· 10 117 posts
Have I understood you correctly that every third beam should be an HEA 120 and the two in between 45x145 pressure-treated wood? When I make an estimate and calculate with 2 kN/m2 in live load/snow load and 0.5 kN/m2 in the self-weight of the wooden beams, not even a 45x220 is sufficient to meet a deflection requirement of 1/300, much less a modern flex requirement. HEA 120 probably holds up. But maybe I've misunderstood it all?
Hello!
Thank you so much for your response. My answer is:
Yes, but in the middle it's denser. It's every other HEÅ120 on positions 13 to 18.
Are you a structural engineer and can I hire your service? There’s no need for a drawing, just that the technical description is correct.
This really needs to be good. But do I have to have HEA 120 in all positions? I have ruled out glulam beams because it would cost 28—30,000 SEK at Beijers.
Thank you so much for your response. My answer is:
Yes, but in the middle it's denser. It's every other HEÅ120 on positions 13 to 18.
Are you a structural engineer and can I hire your service? There’s no need for a drawing, just that the technical description is correct.
This really needs to be good. But do I have to have HEA 120 in all positions? I have ruled out glulam beams because it would cost 28—30,000 SEK at Beijers.
Moderator
· Stockholm
· 56 254 posts
But is 120 really enough for the steel beams? We have a 5m long HEA 180 in the intermediate floor in one place here in the house.
HiH hempularen said:
Your question can only be answered by the engineering. The only thing I can add is that maybe there are different conditions inside the floor of a house with greater loads compared to a deck?
Self-builder
· Arvika
· 1 527 posts
Sizing the roof so that it holds and does not sag too much is no problem to solve. However, there is a risk that it will sway when walking on the deck. Solving the swaying problem is a bit more complicated and will likely involve increased dimensions compared to just sizing so that they hold and do not sag too much.
Yes, you are probably right.B bossespecial said:Designing the roof so that it holds and doesn't sag too much is not a problem to solve. However, there's a risk that it will sway when walking on the terrace. Solving the swaying issue is a bit more complicated and will likely require increased dimensions compared to just designing it to hold and not sag too much.
I have now had a structural engineer calculate this, and it has resulted in each of the positions having an HEB120. The sway and deflection will be minimal. It also withstands a minimum of 400 kg per square meter.
Hi see the answer below - with HEB120 at each position, this is more than sufficient.Y Yngve Levin said:
Self-builder
· Arvika
· 1 527 posts
How close will the beams be placed and what were your plans for the rest of the roof construction?
Member
· Blekinge
· 10 117 posts
As bossespecial points out, it is tricky to make it not too wobbly. As an alternative, I would suggest stronger and sparser steel beams as the primary support structure, possibly c/c 2400, and then wood perpendicular with c/c 600 as the secondary support structure. It's possible to recess the wood between the steel flanges to keep the height down. Assuming a snow load/useful load of 2 kN/m2 and a self-weight of 0.5 kN/m2 (estimates, must be verified), it might work with HEB 160 for the steel and 45x170 C24 for the wood. Just a thought.
The spacing should be 300 cc due to the specifications for the UPM-decking etc. on top. With a spacing of 300cc over approximately 9600 meters, there will be 31 truss positions, meaning 33 intervals of 300 mm with HEB 120 cc 300 at all positions and gable wall at both ends. Tongued and grooved boards on top of the joists, on top of which joists/regars are placed at the same spacing and positions as the trusses. Inside the H-beams, a 90 stud will be glued, which itself forms a recess for the longitudinal construction of the inner ceiling. This also braces against the shear forces. The project is not complete, but as far as HEB and UPM are concerned, it's more or less finalized now.B bossespecial said:
Hi - see my response below to bossespecial. It is anchored with a structural engineer. But with that said, maybe my current solution is not optimal. But for every 300cc, the UPM decks must have support all the way. UPmn is sort of on rails (the floor structure). I really appreciate your thoughts!J justusandersson said:As bossespecial points out, it's tricky to make it not too wobbly. As an alternative, I would suggest more robust and sparser steel beams as the primary framework, preferably c/c 2400, and then wood perpendicular with c/c 600 as the secondary framework. The wood can be recessed between the steel flanges to keep the height down. If you consider snow load/useful load of 2 kN/m2 and self-weight of 0.5 kN/m2 (guesses, need verification), it could work with HEB 160 for the steel and 45x170 C24 for the wood. Just a thought.
Member
· Blekinge
· 10 117 posts
It's easy to lay the crosswise wooden beams at c/c 300 mm, even though it requires twice as many.
