What should be the sequence if you are going to insulate the upper floor?

a.
1. air gap
2. lining
3. insulation
4. installation of skylights
....

Or rather, at what stage should the skylights be installed?
 
jump to construction technology with you ;)
 
I was about to start installing skylights, but it probably doesn't matter...
 
mats_o said:
jump to construction technology with you ;)
No problem :D

Do you know the answer?
 
No more who have suggestions and KNOW?
 
C
Start with all the framework parts before inserting insulation, it will definitely be easier. And I also count doors and windows etc. as framework parts.
 