It's starting to be time to pour the floor in the basement and I'm wondering from whom one buys concrete? Delivery with truck + chute is what's relevant.

Assume it's about 3.5 cubic meters or so, how much time do you have to get this onto the floor before the truck has to go back?

How many people should there be to manage it?
 
Check with nettobetong.
I think two to three men might be sufficient, but you can also ask nettobetong about that.
I used them for my slab.
 
Thanks for the tip, I'm going to call them today.
 
Drove just 2.25 on the slab, there were two of us plus the driver and it would have been good with one more person, then we would have kept pace with how quickly he could unload.
 