I am going to cast a slab for a heat pump type CTC EcoAir 614M and found some tips on variations in the forum. Someone suggests casting pipes/slab, someone else a thicker slab. I was thinking of the version with digging out about 40 cm, laying about 20 cm of 8-16 macadam and 19 cm of concrete with reinforcing mesh in a 130x70 cm frame. Are these unnecessarily thick layers? Any other tips, thoughts, or advice from someone who has done similar?
 
  • Like
hemkört
  • Laddar…
It really felt like overkill to use such a thick slab for a heat pump; I would add more gravel and just cast 10cm, which is strong enough for the outdoor unit.

If you dig out properly and fill with gravel, you'll also have a stenkista for condensation.
 
Thank you for the response. I was also unsure about the thickness, so that was good input. The installer suggested that we should channel the condensate water into the adjacent downspout that leads to a stenkista.
 
In comparison, I cast a 12cm slab for our sauna, it became that thick because of clay, so I wanted a stable slab if it was going to heave due to frost.

So, if you dig out 40cm and fill with 30-35cm of 8-16 and cast a 10cm slab there, it will be great.

At least dig an extra 20cm around the perimeter that you fill with gravel.

You could probably have gotten away with just removing the turf and casting a slab, but a bit more work with digging isn't so bad, and it's harder to fix afterwards.
 
  • Like
Fuga
  • Laddar…
I have quite muddy ground, but if 12 cm works for a sauna, it should be perfectly fine for a heat pump as well. Is the thickness of the macadam layer important with regard to handling frost?
 
Clay is very sensitive to deep frost, a wet autumn followed by cold without snow can cause it to shift.

The larger the area around the slab that is excavated and replaced with gravel, the better.

I don't know where you live, but I don't think you need to worry about it shifting if you follow the above description.
If you're still worried, you can always insulate the slab so the frost doesn't penetrate as deeply.

Then you replace 10cm of gravel with polystyrene or dig 10cm deeper. So when you have excavated for the slab, you fill with gravel until you are 15cm below ground level and then insulate the entire graveled area. Build the form on the polystyrene and pour the concrete.

The slab will end up 5cm above ground level, and you can place the soil with a slight slope from the slab and cover the polystyrene beneath.

I let the polystyrene extend only 30cm beyond the slab for the sauna.

It's only your ambitions that set the limits, you can certainly complicate it more if you want. But I don't think you should overthink it so much.
 
  • Like
Fuga
  • Laddar…
It's in the Stockholm area. Should be fine with about 30 cm of gravel and 10 cm of slab then?
 
B
I think I poured about 7cm for my air-to-water heat pump. It weighed around 160kg. No problems.

The neighbor's air-to-water heat pump of the same size was placed on a couple of garden slabs.

It might be good to consider condensation water, so you don't create an ice rink. Stockholm often has above freezing temperatures during winter, so maybe you don't have to overdo it too much, but there will be quite a bit of ice if it's below freezing for a few consecutive weeks.
 
  • Like
hemkört and 1 other
  • Laddar…
Thank you for the response. How did you handle the base under the slab?
 
An acquaintance previously worked with foundations in the Stockholm area and poured slabs for storage and similar structures. They simply removed the top layer, then insulated with 10 cm and poured on top of that. They never had to redo any jobs because of this.
 
Pouring a slab sounds like a bit of overkill to me. I dug out a small stone crate and set it on garden slabs.
 
  • Like
Fuga
  • Laddar…
B
F Fuga said:
Thanks for the reply. How did you deal with the substrate under the slab?
Dug out topsoil, about 20cm. Then added gravel almost up to ground level, so the slab is slightly above the ground. Just packed the gravel with my feet.

It's probably overkill, but it didn't cost much to do.
 
  • Like
Fuga
  • Laddar…
Remember to have runoff from the foundation for stormwater or similar.

I cast in a drainage pipe that I connected to stormwater.
 
  • Like
Fuga
  • Laddar…
This is how I made my "slab" for air/water (ctc)

Since Ctc already stands on legs as it comes, I cast about 10 cm over the existing paving stones to raise it a bit at least.
 
  • Concrete slab for air-water heat pump with tools, wheelbarrow, and gravel around a house's exterior with brick walls and windows.
  • Like
Fuga
  • Laddar…
Very nice. Thickness? How did you do under the plate? Might be a detailed question, but how did you achieve the beveled edge? It looks very good. How much margin did you choose for the dimension of the plate beyond the leg distances on your CTC?
 
Vi vill skicka notiser för ämnen du bevakar och händelser som berör dig.